Works according to Iberdrola's plan to enhance the electrical reliability in the four Data Centers (CPDs) located in the SETOM area through the implementation of two redundant power lines.
The works involve the use of two completely independent power branches, both electrically and physically, each of which is capable of handling the entire load on its own. We have left an installation with a double redundant branch, N+N, which meets the four fundamental requirements necessary in a Data Center (CPD).
The works were carried out without interrupting the service of the facilities, as an essential requirement from the property, which could not afford to be without them to avoid jeopardizing the supply to the affected areas.
The CPDs executed simultaneously are: